What's the difference between an RFQ and an RFP?
An RFQ asks for a price on something already specified, so the replies can be compared line by line. An RFP describes a problem and asks each supplier how they'd solve it, and the buyer judges the approach, experience and price together.
| Question | RFI | RFQ | RFP |
|---|---|---|---|
| The buyer sends one when | They need to know who could do the work | The drawing, quantity and date are settled | They know the problem but not the answer |
| What comes back | A capability reply, with no price | A quotation with the price, lead time, terms and a validity date | A proposal with the approach, a timeline and a price |
| Replies are compared on | Who can do it, and who goes on the shortlist | Price and lead time, like for like | Approach, experience and price together |
| A line from one | Can you machine and anodise 6082-T6 aluminium brackets, and what batch sizes suit you? | Please quote 250 off BRK-210 rev C, clear anodised, delivered to our Telford site by 30/11/2026. | Propose how you would supply the BA-400 bracket assembly as a finished, labelled kit, and any design change that would lower its cost. |
The steps from an RFQ arriving to an order are in What is an RFQ?
What's the difference between an RFI and an RFQ?
An RFI asks whether you could do the work, and nobody prices anything yet. An RFQ asks for a firm price the buyer could order against, so it has to come with the drawing, revision, quantity and date.
An RFI asks for
- What you make, and the materials you work with
- Your machines and spare capacity
- Your approvals and how you inspect
- Batch sizes and lead times that suit you
- A contact for technical questions
An RFQ asks for
- A unit price at each quantity
- One-off charges, such as tooling
- A lead time from order
- Delivery and payment terms
- The date the price holds until
How do you answer an RFI, an RFQ or an RFP?
Reply in the form the buyer asks for, by their deadline.
- RFI
- Answer what was asked, with the machines, materials and approvals that fit the work. Leave prices out unless the buyer asks, because nothing is specified yet.
- RFQ
- Send a quotation to the revision and quantity asked, with price breaks, one-off charges, a lead time and a validity date. Chase anything missing before you price it.
- RFP
- Answer every question in the buyer's order, then set out your approach, the timeline, the price and what you assumed. If all the RFP really wants is a price, reply as you would to an RFQ.
The quotation template sets out each line of an RFQ reply, with a filled-in quote for the brackets.
Which should you send to your own suppliers?
Send an RFQ for anything you can specify, such as anodising for a batch of brackets, so the prices come back in a form you can compare. If you don't know who could do the work, send a short RFI to a few suppliers first and the RFQ only to those who can. Keep RFPs for work where you want the supplier's ideas, such as a fixture they'd design for you.
The RFQ template lists every detail an RFQ should carry, with a filled-in RFQ for 250 brackets.
Do public sector buyers send RFIs?
They can ask suppliers questions before they publish a tender. The Procurement Act 2023 calls this preliminary market engagement, and its purposes include identifying suppliers that may be able to supply what's needed. Answer one the way you'd answer an RFI.
The tender that follows runs on the buyer's forms and deadline. What is a quotation? covers how a tender differs from a quote, and where public contracts are listed.
Can AI help answer RFIs, RFQs and RFPs?
AI can pull every question out of a long RFP into a checklist, and draft RFI answers from your standard capability text. On an RFQ it can log the part, revision, quantities and dates, and flag what's missing. Whether to reply, and the price, stay with your people.
Give it
- The request and its attachments
- Your standard capability answers
- Past replies to the same customer
A person checks
- Every question has an answer
- No price or date you haven't agreed
- Whether to reply at all
The free check shows which quoting or order job is worth handing over first, and what it costs you now.