Job costing template

A free job cost sheet in Excel, Word and PDF. The Excel version adds up the costs, works out your overhead rate and sets the actuals beside the estimate.

Last checked 05/10/2026. Free, no email.

A filled-in job cost sheet

The job behind the quotation example: 250 machined aluminium brackets, costed at £1,750 and quoted at £8.40 each with a 20% mark-up. Machining ran 1.5 hours over and five blanks were scrapped at first-off, so the job made £231.25 instead of £350.

[Your company name]

Job cost sheet

Job number
WO-3318
Customer and quotation
[Customer company], Q-2026-0142
Part and drawing revision
BRK-210 rev C, mounting bracket
Quantity
250
Costed by and date
[Name], 05/10/2026
Actuals from
Job cards and invoices, 13/11/2026
Job cost, estimate against actual
CostEst. qtyRateEstimateActual qtyActualVariance

Materials

6082-T6 plate, 10 mm, cut blanks

250£2.15£537.50255£548.25+£10.75

Labour

Load, deburr, inspect and pack

12.5 h£24.00£300.0014.0 h£336.00+£36.00

Machine time

Machining centre, setup and two operations

15.0 h£30.00£450.0016.5 h£495.00+£45.00

Outside processes

Clear anodise, 250 parts

250£0.77£192.50250£192.50£0.00

Overheads

On machine hours

15.0 h£18.00£270.0016.5 h£297.00+£27.00
Total cost£1,750.00£1,868.75+£118.75
Margin, 20% on cost£350.00£231.25−£118.75
Price£2,100.00£2,100.00
Price each, 250 off£8.40

Estimate is the estimate quantity times the rate. Actual uses the same rate: type over it if a price changed. Variance is actual minus estimate, so a positive figure means the job cost more than you estimated. The price is total cost plus your mark-up; divide it by the quantity for the unit price on your quote. The downloads add a unit column and an overhead rate sheet.

What is job costing?

Job costing is working out what one job costs you: the material, labour and machine hours, outside processes and a share of the overheads. You do it before the job, when the estimate sets your price, and after it, when the actuals show whether the job made the margin you quoted.

What goes on a job cost sheet?

One line for each cost on the job, with a quantity, a rate and a cost, once for the estimate and again for the actual.

  1. Materials are raw material and bought-in parts from the bill of materials at today's prices, plus offcuts and setting-up scrap.
  2. Labour is hours on the job at what an hour of that person costs you, which is their pay plus employer's National Insurance, pension and holiday, spread over the hours they book to jobs.
  3. Machine time is setup and run hours at your machine rate. If one person minds a machine for the whole cycle, count those hours once.
  4. Outside processes are work sent out, such as anodising, at the supplier's price plus carriage.
  5. Overheads are everything that isn't on a job, such as rent, power and the office, charged through your overhead rate.
  6. Margin is what you add to cost. The sheet adds a mark-up on cost, so 20% on £1,750 is £350. A 20% margin on the price needs a 25% mark-up.

To price at a margin instead, the markup calculator works out the markup it needs and the price with VAT.

How do you fill in a job cost sheet?

Fill in the estimate columns when you quote, from the drawing, the bill of materials and your routing. Fill in the actual columns when the job is done, from job cards, timesheets and supplier invoices.

How do you set an overhead rate?

Add up a year's overheads, then divide them by the hours you expect to book to jobs in that year. £180,000 of overheads over 10,000 booked hours is £18.00 an hour, so a job with 15 machine hours carries £270 of overhead.

  1. List a year's overheads from last year's accounts: rent and rates, power, staff who don't book to jobs, insurance, maintenance and machine finance.
  2. Count the hours you'll book to jobs: machines or people, times hours a week, times working weeks, times the share that goes on jobs.
  3. Divide the overheads by the hours. That's your overhead rate.
  4. Choose machine hours or labour hours, and keep to it. Machine hours suit a machine shop, and labour hours suit fabrication and assembly.
  5. Work it out again when overheads or workload change. A rate set in a busy year undercosts every job in a quiet one.

If your machine rate already includes overheads, leave the overhead line empty, or you'll charge them twice.

What do you do with the variance?

Read it line by line, because a total that looks fine can hide a line that ran over. One line over on one job can be bad luck, but the same line over on three jobs means the time or rate you estimate with is wrong. Correct it, and price repeat orders from the actuals.

On the bracket job, the £118.75 over came from machine time £45.00, labour £36.00, overheads £27.00 and material £10.75. If the next batch runs over too, raise the times you estimate that part with.

How does job costing feed a quotation?

The price on the job cost sheet, divided by the quantity, is the unit price on your quote: £2,100 for 250 brackets is £8.40 each. Cost fixtures, programming and inspection reports separately, because they go on the quote as one-off charges. For price breaks, cost the job again at each quantity.

Setup hours stay much the same however many you make, so the price each falls as the batch grows. The bill of materials template gives you the material lines, and the quotation template takes the price.

Can AI help with job costing?

AI can do the gathering: pulling booked hours from job cards, matching supplier invoices to the job, filling in the actual columns and flagging the lines that ran over. Your estimator sets the times, the rates and the price.

Give it

  • Job cards and timesheets
  • Supplier invoices and delivery notes
  • Past job cost sheets for the same part

A person checks

  • Hours are booked to the right job
  • Invoices sit on the right lines
  • Any time or rate you change for next time